top of page


New DEPOT WALKWAYS
NEVILLE HILL DEPOT WALKWAYS


Customer
NORTHERN TRAINS LIMITED

Project Duration
4 WEEKS

Location
LEEDS

RTS Lead
JAMES SMITH

Project Scope
DESIGN AND BUILD DEPOT ACCESS WALKWAYS
Safe walking routes were required to allow depot staff access between stabled trains at Neville Hill depot in Leeds. Northern Trains enlisted the assistance of RTS to provide GRP walkways and lighting within a constrained depot environment.
Innovative lighting solutions were required to meet Network Rail gauging standards and provide suitable Lux levels and safe access.
An LED lighting solution was installed resulting in excellent visibility and safe access in all weathers, whilst maintaining compliance to all standards.
bottom of page