DEPOT ACCESS PLATFORMS
DRIVER ACCESS 'HOP-UP' PLATFORMS


Customer
STADLER

Project Duration
20 MONTHS

Location
MERSEYSIDE - 3 LOCATIONS

RTS Lead
JAMES SMITH

Project Scope
DESIGN, BUILD AND COMMISSION DRIVER ACCESS PLATFORMS
Our client, Stadler had a requirement for the design, installation and commissioning of access platforms for driver accessibility at three locations (Southport, New Brighton and West Kirby).
RTS supported the client with our design services, sharing our expert knowledge and dedicated design team to incorporating the Civils, M&E, Track, Signalling and ETE elements to form fit for purpose solutions to the client's request.
Following design completion, RTS installed walkways and driver access Hop-Up platforms to all locations.
To facilitate the installation of the hop up – amendments to the track signalling and third rail power were undertaken during safety critical blockades.